1. (TCO 8) ABC Motors, Inc. wants to increase capacity by adding another wheel balancer. The fixed costs for the machine are $16,000, and its variable cost is $4.50 per unit. ABC charges $8.50 to balance one wheel, the break-even point for the balancer. What is her break-even point in units? 2. (TCO 9) A full-service restaurant is considering opening a new facility in a specific city. The table below shows its ratings of four factors at each of two potential sites. Factor Weight Wind City State Line  Affluence of local population .40 25 25  Traffic flow .20 50 20  Parking availability .10 30 40  Growth potential .30 10 30  The score for Wind City is _____ and the score for State Line is _____. 3. (TCO 8) A fleet repair facility has a design capacity to repair 800 trucks per month. However, because of scheduled maintenance of their equipment, management feels that they can repair no more than 600 trucks per month. Last month, two of the employees were absent several days each and only 500 trucks were repaired. What is the utilization of the repair shop last month? 4. (TCO 8) A fleet repair facility has the capacity to repair 800 trucks per month. However, because of scheduled maintenance of their equipment, management feels that they can repair no more than 600 trucks per month. Last month, two of the employees were absent several days each, and only 300 trucks were repaired. What was the efficiency of the repair shop last month? 5. (TCO 8) Design capacity is the 6. (TCO 8) Fixed costs are 7. (TCO 9) When making a location decision at the region or community level, which of these would be considered? 8. (TCO 9) Globalization of the location decision is the result of all of the following except 9. (TCO 9) Evaluating location alternatives by comparing their composite (weighted-average) scores involves 10. (TCO 8) An operation that is the limiting factor or constraint is called a _____.1. (TCO 8) ABC Motors, Inc. wants to increase capacity by adding another wheel balancer. The fixed costs for the machine are $16,000, and its variable cost is $4.50 per unit. ABC charges $8.50 to balance one wheel, the break-even point for the balancer. What is her break-even point in units? 2. (TCO 9) A full-service restaurant is considering opening a new facility in a specific city. The table below shows its ratings of four factors at each of two potential sites. Factor Weight Wind City State Line  Affluence of local population .40 25 25  Traffic flow .20 50 20  Parking availability .10 30 40  Growth potential .30 10 30  The score for Wind City is _____ and the score for State Line is _____. 3. (TCO 8) A fleet repair facility has a design capacity to repair 800 trucks per month. However, because of scheduled maintenance of their equipment, management feels that they can repair no more than 600 trucks per month. Last month, two of the employees were absent several days each and only 500 trucks were repaired. What is the utilization of the repair shop last month? 4. (TCO 8) A fleet repair facility has the capacity to repair 800 trucks per month. However, because of scheduled maintenance of their equipment, management feels that they can repair no more than 600 trucks per month. Last month, two of the employees were absent several days each, and only 300 trucks were repaired. What was the efficiency of the repair shop last month? 5. (TCO 8) Design capacity is the 6. (TCO 8) Fixed costs are 7. (TCO 9) When making a location decision at the region or community level, which of these would be considered? 8. (TCO 9) Globalization of the location decision is the result of all of the following except 9. (TCO 9) Evaluating location alternatives by comparing their composite (weighted-average) scores involves 10. (TCO 8) An operation that is the limiting factor or constraint is called a _____.

Leave a Reply

Your email address will not be published. Required fields are marked *